Today was roof day for the building. John first rolled out the felt, then placed the shingles on the roof. Not a lot of pictures because with the pitch of the roof, you really cannot see the shingles.
It was a cold day today. I don't think it got above 60 degrees, but that was okay for laying the shingles. It wasn't so hot, and this week promises to stay cool; then it will warm up once again.
So the roof was finished today and then Terry and I had to make another trip to the lumber yard to order the next truckload of materials. We get a list of what to order for each phase. It is working really well because we don't have a lot of material sitting outside for long. The order is to be delivered by 10 a.m. tomorrow, but there is work that can be done before it arrives.
Till next time. . .
Dale